dCache 1.8 / SRM 2.2 Deployment
Tier I's
The table below summarizes milestones in the deployment process of dCache 1.8 (SRM2.2) for the Tier I sites. Please note that at any time, any site may change the scheduling without further notice to dCache.org.
| Site | Week of Upgrade | Comment |
|---|---|---|
| NDGF | Oct 29 | Agreed |
| gridKa | Nov 5 | Agreed. Downtime will be Nov 6, Tuning Nov 7 |
| Workshop Edinburgh | Nov 12 | Tuesday/Wednesday 13/14 |
| SARA | Nov 19 | Agreed |
| IN2P3 | Nov 26 | Agreed |
| NDGF | Dec 3 | Agreed (Second shot) |
| RAL, Triumf | Dec 3 | Agreed |
| BNL | Dec 10 | rather sure |
| FNAL | Dec 12 | Agreed |
| PIC | Dec 17 | Agreed |
Tier II's
Theoretically, Tier II's may upgrade as soon as the dCache 1.8 production version will be available, which will be the second week of November. Nevertheless we would recommend to watch the upgrades of the Tier I's carefully to estimate the efforts for your site. Furthermore, we would recommend to consider to participate the Edinburgh workshop in November to learn more on how to setup dCache according to the requirements of the experiments.
OSG Tier II's : End of February, dCache 1.8 will be packaged with the OSG VDT distribution, which is the point in time from which on OSG will officially support dCache 1.8.
Last Modified by Patrick @ Sat Nov 22 04:14:41 2008